Key Points For Inspection Before Hot Melt Glue Production Line Goes Into Production | JCT Machinery
Preliminary inspection after installation (static inspection)
1. Equipment Appearance and Connections
- All equipment (sigma mixer, reactor, extruder, transfer pump, molding system, cooling system, etc.) must be free of damage, deformation or rust.
- All flanges, bolts and seals must be securely installed and tightened.
- Pipelines must be properly connected, with clear flow direction markings (especially for thermal oil, cooling water and vacuum lines).
- Cables must be neatly routed, protective conduits must be intact, and no exposed wires or damaged casings should be present.
2. Safety Devices and Protective Measures
- The safety valve, pressure gauge, and thermometer are all installed and readings are normal.
- The emergency stop switch is functioning properly and clearly located.
- External protective covers for all rotating components (such as the extruder screw and agitator shaft) are fully installed.
- The grounding wire and insulation resistance test have passed (≥1MΩ).