Key Points For Inspection Before Hot Melt Glue Production Line Goes Into Production | JCT Machinery

 Preliminary inspection after installation (static inspection)

1. Equipment Appearance and Connections

  • All equipment (sigma mixer, reactor, extruder, transfer pump, molding system, cooling system, etc.) must be free of damage, deformation or rust.
  • All flanges, bolts and seals must be securely installed and tightened.
  • Pipelines must be properly connected, with clear flow direction markings (especially for thermal oil, cooling water and vacuum lines).
  • Cables must be neatly routed, protective conduits must be intact, and no exposed wires or damaged casings should be present.
2. Safety Devices and Protective Measures
  • The safety valve, pressure gauge, and thermometer are all installed and readings are normal.
  • The emergency stop switch is functioning properly and clearly located.
  • External protective covers for all rotating components (such as the extruder screw and agitator shaft) are fully installed.
  • The grounding wire and insulation resistance test have passed (≥1MΩ).

For more information, you can click to see, or contact us: +86-181 3837 3963 (Whatsapp, Wechat) or chemicalmixingtank2004@gmail.com.

评论

此博客中的热门博文

Creating The Perfect Combination For High-quality Paint | JCT Machinery

The Construction Boom Has Driven Continued Growth In SIlicone Sealant Market | JCT Machinery

Double Planetary Mixer Shipment Performance And Application Recommendation | JCT Machinery